Pasadena to Azusa Alignment Project Construction Notices

Thursday, July 9, 2015 thru Friday, July 10, 2015: Full closure of Mountain Ave at Duarte Rd for one night, from Thursday, July 9, 2015 at 8 PM to Friday, July 10, 2015 at 6 AM, to allow crews to stripe the roadway surface, Monrovia.

Saturday, August 15, 2015: Duarte Road closed from Hope Drive to Highland Avenue to vehicular traffic for station dedication ceremony, Duarte.

April 17, 2015 thru early June 2015: Nightly Train Testing from Pasadena to Irwindale.

May 16 – 17, 2015: Highland Ave weekend street closure at Duarte Rd., Duarte.

February 2015 thru Summer 2015: Train Testing & Extended Work Hours.

February 2015 thru Summer 2015: Letter to Our Neighbors Regarding Train Testing and Extended Work Hours.

February 23 – 24, 2015; March 6 – 7, 2015: Water line tie-in work at the intersection of east frontage street Irwindale Road and Avenida Padilla. Water will be shut down for a short period of time, Azusa.

Jan. 8 – 23, 2015: Arboleda St at Michillinda Ave. Arbodela St will be closed daily at Michillinda Ave on Jan. 8 – 17, 2015, from 8 AM to 3:30 PM, except Sundays. The following week, the street will be closed during nighttime on Jan. 19 – 23, 2015, from 8 PM to 6 AM, Pasadena.

Dec. 8 – 19, 2014: Initial train testing for the project is taking place, Mon-Fri; 8 AM to 5 PM. There will be short-term impacts to street traffic at the following intersection crossings as the train moves through each crossing on the first and last day: First Ave/Santa Clara St (Arcadia), Mayflower Ave (Monrovia), Magnolia Ave (Monrovia), Myrtle Ave (Monrovia), California Ave (Monrovia), Mountain Ave (Monrovia & Duarte), Buena Vista St (Duarte), and Highland Ave (Duarte).

November 19, 2014: Palm Dr at the railroad bridges will be fully closed to thru-traffic, from 8 AM to 6 PM, to allow crews to complete final paving work, Azusa.

October 17 – 18, 2014: A final full closure of the Mountain Ave and Duarte Rd intersection will be implemented to realign the traffic lanes in their final configuration and perform the striping of the intersection. Following this work, the intersection will fully re-open to thru-traffic and no additional full closures of the intersection are anticipated, Monrovia & Duarte.

October 7 – 10, 2014: Palm Dr will be closed daily, from 7 AM to 6 PM, at the railroad bridge to allow crews to install decorative concrete panels on the north side of the bridge, Azusa.

September 26 – 29, 2014: Full weekend intersection closure of Mountain Ave and Duarte Rd. Mountain Ave, south of Duarte Rd, to re-open on September 29, 2014, Monrovia & Duarte.

Beginning September 21, 2014 for three weeks: Huntington Dr will be closed to thru-traffic at Second Ave in either eastbound or westbound direction (not concurrently) and thru-traffic on Second Ave at the intersection will be restricted to allow crews to paint the bridge girders. No work will be performed on Friday or Saturday nights, Arcadia.

August 24, 2014 – September 26, 2014: Mountain Ave will be fully closed to thru-traffic from the center of Duarte Rd south through the intersection. Duarte Rd will be open to thru-traffic in both eastbound and westbound directions, Monrovia & Duarte.

Beginning August 12, 2014: Beginning August 12, 2014 for approximately six weeks, Sundays thru Thursdays ONLY, from 8 PM to 6 AM: Huntington Dr will be closed to thru-traffic at Second Ave in either eastbound or westbound direction (never concurrently), while no thru-traffic will be allowed on Second Ave at Huntington Dr, to install the cross beams and deck steel, Arcadia.

September 16 – 17, 2014: The intersection of Huntington Dr and Second Ave will be fully closed to thru-traffic to pour concrete atop the newly constructed light rail bridge structure, Arcadia.

May 12, 2014 – August 24, 2014: Mountain Ave will be fully closed north of Duarte Rd for five months, in the first of two phases, for construction of grade crossing improvements, Monrovia & Duarte. Update: June 10, 2014 – late August 2014: Extended work hours to expedite construction.

August 22 – 24, 2014: The entire intersection of Mountain Ave and Duarte Rd will be closed to thru-traffic to reconfigure the traffic lanes and prepare for the next phased closure, Monrovia & Duarte.

August 21 – 22, 2014: Myrtle Ave and Pomona Ave will each be fully closed on separate nights, from 8 PM to 6 AM, to thru-traffic to allow crews to install underground conduits, Monrovia.

August 11 – 18, 2014: Partial lane closures on South Primose Ave, south of West Pomona Ave, to allow for water line tie-ins, Monrovia.

March 31, 2014 – August 15, 2014: Virginia Ave will be fully closed to thru-traffic in both directions just south of Foothill Blvd and north of Sixth St, Azusa.

August 8 – 12, 2014: The intersection of Huntington Dr and Second Ave will be fully closed to thru-traffic to install the bridge girders, Arcadia.

August 4 – 8, 2014: Daytime closures of the access road from eastbound Colorado Blvd onto southbound Baldwin Ave, Arcadia.

July 20, 2014 – August 1, 2014: Nighttime closures of Second Ave at Huntington Dr, Arcadia.

July 26, 2014: Full closure of Duarte Rd at Hope Dr to allow for underground conduit installation, Duarte.

July 24 & 25, 2014: Myrtle Ave and Pomona Ave will each be fully closed on separate nights, from 8 PM to 6 AM, to thru-traffic to allow crews to install underground conduits, Monrovia.

June 29, 2014 – July 24, 2014: Southbound Baldwin Ave, from the I-210 Freeway overpass to just south of Colorado Blvd, will be fully closed to thru-traffic in a series of full, nighttime and daytime closures to allow crews to install underground duct banks and electrical vaults, Arcadia.

April 21, 2014 – August 2014: Magnolia Ave will be fully closed for four months, between Pomona Ave and Genoa St, for construction of grade crossing improvements. A free shuttle service will be provided to assist pedestrians around closure from 7 AM to 7 PM daily, Monrovia.

June 9, 2014 – July 22, 2014: Eastbound Foothill Blvd will be fully closed to thru-traffic between Vernon Ave and Orange Ave during nighttime/early morning hours on June 9 – 10, 2014 and July 8 – 22, 2014, Azusa.

May 1, 2014 – June 30, 2014: Crews will be working extended work hours from 6 AM to 8 PM for Gold Line Bridge track work, Arcadia.

June 24, 2014 – mid-July 2014: Genoa St at Magnolia Ave will be closed to thru-traffic to allow crews to upgrade the sidewalks and install a new concrete curbed median, Monrovia.

Dec. 2012 – June 2014: Construction Activities within Railroad Corridor, Monrovia.

July 19, 2014: Full closure of Central Ave and Business Center Dr at Highland Ave to allow for underground conduit installation, Duarte.

June 2, 2014 – July 7, 2014: Westbound Foothill Blvd will be fully closed to thru-traffic between Vernon Ave and Orange Ave during nighttime/early morning hours on June 2 – 6, 2014 and June 23, 2014 – July 7, 2014, Azusa.

July 8, 2014: 9th St at Pasadena Ave will be fully closed to thru-traffic to allow crews to install new traffic signals, Azusa.

June 20 – 21, 2014: Foothill Blvd will be fully closed to thru-traffic between Vernon Ave and Orange Ave, Azusa.

June 17, 2014: Mayflower Ave will be narrowed to one lane of traffic in each direction between Diamond St/Evergreen Ave and Fano St for street paving, Monrovia.

June 9 – 20, 2014: Lane closures on Santa Clara St between Santa Anita Ave and First Ave, Arcadia.

May 20, 2014 – June 10, 2014: Extended work hours at Mountain Ave to install storm drain, Duarte.

May 5 – 10, 2014: Nighttime lane closures on southbound Rosemead Blvd (between Foothill Blvd and Colorado Blvd), Pasadena.

End of July 2013 – mid-May 2014: Long-Term Lane Closures on  San Gabriel Ave, Azusa.

May 9 – 11, 2014: The intersection of Mountain Ave and Duarte Rd will be fully closed during the weekend to thru-traffic. Afterwards, Duarte Rd will re-open to one lane of traffic in each direction, Monrovia.

April 28, 2014 – May 13, 2014: Street improvement work on Flower St, between La Porte St and St Joseph St, just north of the railroad corridor, Arcadia.

March 17, 2014 – May 4, 2014: Nighttime lane closures on northbound Rosemead Blvd (between Foothill Blvd and Colorado Blvd), Pasadena.

April 25 – 27, 2014: Weekend work to encase underground waterline, Azusa.

April 25 – 28, 2014: San Gabriel Ave will be fully closed to thru-traffic in both directions between Ninth St and Foothill Blvd, Azusa.

April 28, 2014 – May 1, 2014: Santa Anita Ave (between Colorado Blvd and Santa Clara St) will be fully closed to thru-traffic for two nights in each direction, Arcadia.

May 5, 2014 – June 2014: Westbound Foothill Blvd will be closed to thru-traffic daily between Vernon Ave and Orange Ave, Azusa.

March 24, 2014 – May 4, 2014: Eastbound Foothill Blvd will be closed to thru-traffic daily between Vernon Ave and Orange Ave, Azusa.

Beginning July 2013: Long-term periodic lane closures on Mountain Ave and Duarte Rd, Monrovia & Duarte.

April 15 – 17, 2014: Full night closure of Myrtle Ave & Duarte Rd intersection, followed by full re-opening of streets in all directions, Monrovia.

Jan. 20, 2014 – May 2014: Myrtle Ave will be fully closed for four months, just north of Duarte Rd, for construction of grade crossing improvements, Monrovia.

March 7 – 10, 21 – 24, 28 – 31, 2014: Foothill Blvd will be closed to thru-traffic in both directions between Vernon Ave and Orange Ave, Azusa.

March 31, 2014 – July 2014: Letter to Our Neighbors Regarding Upcoming Closures of Virginia Ave at Railroad Crossing, Azusa.

March 7, 2014 – June 2014: Letter to Our Neighbors Regarding Upcoming Closures of Foothill Blvd at Railroad Bridges, Azusa.

Late Oct. 2013 – Early March 2014: Full nighttime southbound closure of Michillinda Ave (between Foothill Blvd. and Colorado Blvd) for installation of underground power and communications duct banks, Pasadena.

Sept. 2013 – March 2014: Long-term closure of intersection and sidewalk at 1st Ave & Santa Clara St, Arcadia. (Updated notice)

March 6, 2014: Temporary lane closures on Santa Anita Ave for street paving, Arcadia.

Feb. 14 – 15, 2014: Nighttime closure of eastbound Foothill Blvd, Azusa.

Feb. 7 – 9, 2014: Underground waterline installation at railroad corridor, Azusa.

Jan. 18 – 19, 2014: Nightly closures of Myrtle Ave/Duarte Rd intersection, Monrovia.

Dec. 2013 – Jan. 2014: Wall construction along Indiana St. (between First Av & Second Av east of where Wheeler Ave dead ends), Arcadia.

Jan. 16, 2014: Nighttime closure of eastbound Foothill Blvd, Azusa.

Beginning August 12, 2013: Retaining Wall Construction within Railroad Corridor between 1-210 Gold Line Bridge and Colorado Blvd, Arcadia.

Jan. 6-9, 2014: Nightly lane closures on Santa Anita Ave for installation of bridge deck beams, Arcadia.

Nov. 16 2013 – end of Feb. 2014: California Ave closed just south of Duarte Rd for second phase of construction of grade crossing improvements, Monrovia.

Jan. 13, 2014: One-day intersection closure of California Ave & Duarte Rd. Streets to re-open in all directions following closure, Monrovia.

Oct. 17, 2013: California Ave crossing FAQs

Jan. 10-12, 2014: Underground utilities relocation on San Gabriel Ave at the railroad corridor, Azusa

July 2013 – Nov. 2013: Long-term lane closures on San Gabriel Ave, Azusa

Mid Oct. – Dec. 2013: Temporary lane closures on intersection of N. Irwindale Ave and Adelante St for construction of Intersection improvements/new traffic signal, Irwindale.

Sept. 26 –  early Dec. 2013: Full closure of Mayflower Ave at railroad crossing (between Duarte Rd and Evergreen Ave) for construction of grade crossing improvements. Monrovia.

Sept. 9, 2013 – Feb. 2014: Long-term closure of intersection at 1st Ave & Santa Clara St. Arcadia.

Nov. 20-22, 2013: Full closure of Palm Dr (at rail bridges) for installation of bridge deck beams for two light rail bridges over Palm Dr, Azusa.

Nov. 16 2013: One-day closure of California Ave/Duarte Rd intersection for construction of grade crossing improvements, Monrovia.

Nov. 8-9, 2013: Full nighttime closure of  Foothill Blvd for traffic lane shift beginning at 7PM, Friday, Nov. 8, 2013 until 7AM Saturday Nov. 9, 2013, Azusa.

Sept. 18, 2013: Permanent Road Closure: Front St (between Santa Clara St and St. Joseph St) to be closed permanently as of Sept. 18. Arcadia.

Nov. 7, 2013: One-day closure of California Ave/Duarte Rd intersection for construction of grade crossing improvements on Thursday, Nov. 7, 2013 from 7AM to 7PM. Monrovia.

Aug. 20, 2013: Permanent Road Closure: Alameda Ave at railroad tracks (between 9th St and Foothill Blvd) closed permanently, as of August 20, 2013, Azusa.

Oct. 30-31, 2013: Full closure of Santa Anita Ave for reconfiguration of traffic lanes from Wednesday, October 30, 2013 at 10PM until 6AM Thursday morning, Arcadia

Oct. 14-21, 2013: Hydrant relocation on Cornell Dr. Cornell Dr. to be narrowed to one lane for both eastbound and westbound traffic during activity, Arcadia

Starting July 2013: Long-term closures on Mountain Ave and Duarte, Monrovia/Duarte 2

Beginning July 2013: Long-term closures on Mountain Ave and Duarte Rd. Monrovia/Duarte 1

Jan. 14 – Sept. 27, 2013: Long-Term Lane Closures on Foothill Boulevard in Azusa

Mar. 9 – Oct. 2013: California Ave closed at railroad crossing (just north of Duarte Rd.), Monrovia

Sept. 24, 2013: Installation of Bridge Deck Beams at Santa Anita Wash Bridge, Monrovia

Feb. 25, 2013 – late Aug. 2013: Railroad Bridge Construction at Santa Anita Wash, Monrovia

Tues. Sept. 10, 2013: Temporary water service interruption – Duarte Rd and California Ave, Monrovia

Week of Sept. 9, 2013: Nighttime track relocation work within railroad corridor between Virginia Ave and Pasadena Ave in Azusa. 

July 30 – mid-August 2013: Utility installation on Flower St, Arcadia

Aug.  6, 2013 – late Aug. 2013: Night (3PM – 12AM) and weekend work along railroad corridor between Dalton Ave in Azusa and Barranca Ave in Glendora.

Aug. 3, 2013 –  late Aug. 2013: Lane closures on Buena Vista St and Duarte Rd for intersection improvements. One lane will remain open in both directions. No left turn will be allowed from northbound Buena Vista St onto westbound Duarte Rd, Duarte

Aug. 22, 2013 & Aug. 24, 2013: Two full closures of the intersection with Duarte Rd this week: (1) Thursday, August 22 from 7PM to 5AM the next morning; (2) all day Saturday, August 24, 2013 from 7AM to 7PM, Duarte.

May 20 – End of Oct. 2013: Long term lane closures for Santa Anita Bridge construction (north and south bound lanes) started May 20, 2013 and will continue for approx 7 months, Arcadia  –  Mandarin Version.

Aug. 9, 2013 – Aug. 12, 2013 & Aug. 16, 2013 – Aug. 19, 2013: Weekend / Overnight work on San Gabriel Ave at Railroad Corridor, Azusa.

End of June 2013 – August 2013: Full closure of Pasadena Ave. at railroad crossing, Azusa

Dec. 3, 2012 – June 30, 2013: Construction Activities within Railroad Corridor in Irwindale, CA

Beginning May 1, 2013: Full closure of Virginia Ave for utility relocation, Azusa

Aug. 1, 2013 – Aug. 5, 2013: Full closure of Palm Dr from 7AM Thursday, August 1, 2013 to 7AM Monday, August 5, 2013 for reight bridge relocation, Azusa

Dec. 2012 – Jul. 2014: Construction Activities within Railroad Corridor in Duarte

Apr. 29 – Through- Late July, 2013: Azusa Ave closed at railroad crossing, Azusa

July 19, 2013 – July 22, 2013: 24-Hours per day work activity at railroad corridor from Citrus Ave to Barranca Ave. Azusa

Dec. 3, 2012 – June 30, 2013: Construction Activities within Railroad Corridor in Irwindale

Oct. 15, 2012 – Jun. 30, 2013: Construction Activities within Railroad Corridor in Azusa

Oct. 15, 2012 – Jun. 30, 2013: Construction Activities within Railroad Corridor in Glendora

July 12 through July 14, 2013: Weekend / night work near Virginia Avenue, Azusa

Feb. 25 – Jun 30, 2013: Railroad Bridge Construction at Santa Anita Wash, Monrovia

Beginning May 2013: Ongoing utility relocation work at Pasadena Ave. requires lane closures, weekend, and nighttime work, Azusa

Feb. 18 through July, 2013: Full closure of Dalton Ave, Azusa

June 17-21, 2013: Utility installation on California Ave – 24-hours per day work activity, Monrovia

Nov. 26, 2012 – May 31, 2013: Station Construction Activities within Railroad Corridor in Duarte, CA

May 28, 2013 through June 16, 2013: Occassional lane closures on Buena Vista St and Duarte Rd, Duarte

Beginning April 23, 2013: Utility relocation work on Mountain Ave., Monrovia/Duarte

Feb. 18 through Late May, 2013:  Dalton Ave. Full Closure, Azusa

May 21 & May 22, 2013:  Intersection Closure at First Ave.  and Santa Clara, Arcadia

May 22, 2013:  Temporary Water Service Interruption, Dalton Ave., Azusa

Jan. 7 – 3rd Week of May 2013:  Extension of Colorado Blvd. Closure, Arcadia

May 3-5, 2013:  Weekend/Nightwork on Virginia Ave. for Utility Installation, Azusa

Jan. 7 – May 3, 2013:  Temporary Closure on Palm Dr., Azusa

Apr. 22 – Apr. 26, 2013:  Street Closure Santa Fe Ave. and Azusa Ave., Azusa

April 24, 2013:  Temporary Water Service Interruption on Foothill Blvd. Azusa

April 30, 2013:  Lane Closures on Huntington Dr., Arcadia

Oct. 29, 2012 – Mar. 31, 2013:  Construction in Railroad Corridor, Azusa

Feb. – Mar., 2013:  Wall Construction in Railroad Corridor, Azusa

Mar. 22-24, 2013:  Freight Track Realignment, Azusa

Mar. 9, 2013:  One-Day Closure California/Duarte Intersection, Duarte

Feb. 4 – Mar. 11, 2013:  Highland Ave. at Duarte Rd. Four Week Closure, Duarte 

Feb. 11-15, 2013:  Lane Closures for Underground Utility Work at Evergreen Ave and Shamrock Ave, Monrovia

Feb. 12, 2013:  Temporary Water Service Interruption, Soldano Ave, Azusa

Feb. 11-13, 2013:  Lane Closure for Tree Removal Work on Santa Anita Avenue, Arcadia

Feb. 7, 2013:  Lane Closure on Northbound Rosemead Blvd., Pasadena

Feb 6-8, 2013:  Lane Closure on Northbound California Ave, Monrovia

Nov. 5 – Dec. 14, 2012:  Lane Closures along Myrtle Ave, Monrovia

Dec. 10, 2012 – Jan. 25, 2013:  Vegetation Removal in Railroad Corridor, Monrovia

Dec. 2012 – Jan. 2013:  5th Ave Pedestrian Tunnel, Monrovia

Jan. 9, 2013:  Water Line Relocation, Azusa

Dec. 5-31, 2012:  Vegetation Removal in Railroad Corridor, Arcadia

Nov. 5 – 16, 2012:  Vegetation Removal in Railroad Corridor, Arcadia

Nov. 30 – Dec. 17, 2012:  Utility Installation within Railroad Corridor, Azusa

Dec. 8, 2012:  Street Closure: N. Virginia Ave at Railroad Crossing, Azusa

Nov. 16 – 18, 2012:  Signal and Crossing System Testing, Azusa

Nov. 27 – Dec. 11, 2012:  Wall Construction within Railroad Corridor, Azusa

Oct. 22 – Nov. 9, 2012:  Removing Existing Railroad Tracks, Azusa

Nov. 2-3, 2012:  Street Closures near Railroad Crossing, Azusa

Oct. 29 – Dec. 10, 2012:  Installation of Underground Utility along Evergreen Ave, Monrovia

Nov. 26 – Dec. 3. 2012:  Vegetation Removal in Railroad Corridor, Duarte

Sept. 26 – Oct. 26, 2012:  Demolition Activity within Maintenance and Operations Facility, Monrovia

Sept. 11 – Oct. 26, 2012:  Removing Existing Railroad Tracks, Azusa

Aug. 1 – Nov. 1, 2012:  Installation of Underground Utilities, Azusa

Aug. 1 – Nov. 1, 2012:  Installation of Underground Utilities, Irwindale

Aug. 1 – Nov. 1, 2012:  Installation of Underground Utilities, Glendora

Sept. 24 – Oct. 5, 2012:  Closure of Magnolia Ave. between Genoa St. and Pomona Ave., Monrovia

Sept. 24, 2012:  Closure of N. Duarte Rd, north of Railroad Corridor, Monrovia

Sept. 4-10, 2012:  Vegetation Removal within Railroad Corridor, Irwindale

Aug. 23 – Sept. 5, 2012:  Vegetation Removal within Railroad Corridor, Azusa

Aug. 23 – Sept. 28, 2012:  Removing Existing Railroad Tracks from
Mountain Ave. to Highland Ave., Duarte

Aug. 20 – Sept. 4, 2012:  Reinforcement of Underground Utility Lines, Azusa

Aug. 7 – Sept. 4, 2012:  Underground Utility Placement on Shamrock Ave., Monrovia

July 31 – Aug. 31, 2012:  Removing Existing Railroad Tracks from Myrtle Ave. to Mountain Ave., Monrovia

July 30 – Aug. 3, 2012:  Vegetation Removal within Railroad Corridor, Azusa

July 30 – Aug. 3, 2012:  Vegetation Removal within Railroad Corridor, Glendora

July 20, 2012:  Underground Utility Examination on Duarte Rd., Monrovia

July 13 – August 10, 2012:  Removing Existing Railroad Tracks from Magnolia Ave. to Myrtle Ave., Monrovia

July 1-31, 2012: Removing Existing Railroad Tracks from S. 5th Ave. to
S. Magnolia Ave., Monrovia

July 9-11, 2012:  Underground Soil Investigation at Existing Railroad Tracks, Irwindale

July 9-11, 2012:  Underground Soil Investigation at Existing Railroad Tracks, Azusa

July 5, 2012:  Underground Utility Examination on Magnolia Ave., Monrovia

July 5, 2012:  Underground Utility Examination on Shamrock Ave., Monrovia

June 19 – July 13, 2012:  Removing Existing Railroad Tracks from S. 5th Ave. to
S. Magnolia Ave., Monrovia

June 19-22, 2012:  Lane Closures for Underground Utility Examination, Pasadena

June 19-22, 2012:  Lane Closures for Underground Utility Examination, Arcadia

June 11-15, 2011:  Full Closure of Colorado Boulevard for Bridge Removal,

June 7, 2012:  Underground Soil Investigation at Existing Railroad Tracks, Glendora

June 6-7, 2012:  Underground Soil Investigation at Existing Railroad Tracks, Azusa1

June 6-7, 2012:  Underground Utility Work near the Existing Railroad Tracks, Azusa2

June 5, 2012:  Underground Soil Investigation at Existing Railroad Tracks, Monrovia

May 29, 2012:  Lane closure for Asphalt Paving on Santa Anita Avenue at Railroad Track Crossing, Arcadia

May 29, 2012:  Underground Utility Examination near the Existing Railroad Tracks, Monrovia

May 30, 2012:  Underground Utility Examination near the Existing Railroad Tracks and Railroad Street Crossings, Monrovia

May 31, 2012:  Underground Utility Examination near the Existing Railroad Tracks and Railroad Street Crossings, Monrovia

June 1, 2012:  Underground Utility Examination near the Existing Railroad Tracks and Railroad Street Crossings, Monrovia

May 24-25, 2012:  Lane Closures for Underground Utility Examination, Pasadena

May 23-25, 2012:  Underground Utility Examination near the Existing Railroad Tracks and Railroad Street Crossings, Monrovia

May 23, 2012:  Underground Utility Examination near the Existing Railroad Tracks and Railroad Street Crossings, Duarte

May 21 – June 15, 2012:  Four-Week Closure of Colorado Boulevard for Bridge Removal, Arcadia

May 21, 2012:  Underground Utility Examination near the Existing Railroad Tracks and Railroad Street Crossings, Arcadia

May 14 – May 23, 2012:  Underground Utility Work at Duarte Rd. and Highland Ave., Duarte

May 7-9, 2012:  Excavation to Verify Bridge Foundations at 2nd Ave. and Huntington Dr., Arcadia,

May 7-8, 2012:  Excavation to Verify Bridge Foundations at Foothill Blvd. between N. Vernon Ave. and N. Angeleno Ave., Azusa

April 30 – May 25, 2012:  Removing Existing Railroad Tracks from Newcastle Park to South 5th Ave., Arcadia

April 30 – May 25, 2012:  Removing Existing Railroad Tracks from South 5th Ave. to South Magnolia Ave., Monrovia

Mar. 22 – Apr. 5, 2012:  Underground Utility Investigation at Railroad Street Crossing, Monrovia

Mar. 22 – Apr. 5, 2012:  Underground Utility and Soil Investigation along the Railroad Including Railroad Street Crossings, Monrovia

Mar. 22 – Apr. 5, 2012:  Underground Utility and Soil Investigation along the Railroad Including Railroad Street Crossings, Duarte

Mar. 20 – Mar. 23, 2012:  Underground Utility Investigation at Railroad Street Crossing, Azusa

Feb. 20 – 24, 2012:  Soil Investigation Along the Railroad, Arcadia and  Soil Investigation Along the Railroad, Monrovia

Jan. 23 – Feb. 17, 2012:  Underground Utility and Soil Investigation along the Railroad Including Railroad Street Crossings, Arcadia,

Jan. 23 – Feb. 17, 2012:  Underground Utility and Soil Investigation along the Railroad Including Railroad Street Crossings, Monrovia

Jan. 23 – Feb. 17, 2012:  Underground Utility and Soil Investigation along the Railroad Including Railroad Street Crossings, Duarte,

Jan. 23 – Feb. 17, 2012:  Underground Utility and Soil Investigation along the Railroad Including Railroad Street Crossings, Azusa

January 9, 2012:  Lane Closures for Soil Investigation, Azusa 

Pasadena to Azusa Alignment Project Community Hotline:
626-324-7098